India: India added more than 18 GVA of new transformation capacity in the first two months of FY27, supported mainly by strong commissioning in the 765 kV class.
According to the latest figures from the Central Electricity Authority, 18,515 MVA of new transformation capacity was commissioned during April and May, considering substations of 220 kV and above. This was well ahead of the planned addition of 12,564 MVA for the period.
The 765 kV category accounted for more than half of the total, with 10,500 MVA commissioned in 2MFY27. Power Grid Corporation of India Ltd contributed 7,500 MVA, while the remaining capacity came from the private sector.
This strong performance also supported interstate grid development. A total of 11,315 MVA of new substation capacity was added on the ISTS side during the period, representing more than 60 % of the total capacity addition.
The 400 kV category performed below target. Against a planned addition of 4,815 MVA, only 2,815 MVA was achieved, with both PGCIL and the private sector falling short of their respective targets.
In the 220 kV / 230 kV category, 5,200 MVA was added, entirely by the state government sector. This was comfortably above the planned 3,249 MVA.
For the full FY27 period, from 1 April 2026 to 31 March 2027, India has targeted 158,339 MVA of new transformation capacity. The 765 kV and 400 kV categories are expected to play a major role, particularly in interstate grid expansion.
Source: T&D India