USA, Orange: Avangrid has advanced work at more than 40 substations and substation facilities across Maine, New York and Connecticut during 2026. Projects include equipment replacements, capacity upgrades, flood protection and automation improvements.
In Connecticut, subsidiary United Illuminating began construction on the Old Town Substation rebuild in Bridgeport, transformer replacement at Ansonia Substation and reliability upgrades at Sackett Substation in North Haven.
The utility also advanced flood protection construction at Singer Substation in Bridgeport and engineering work for flood mitigation at Grand Avenue-Mill River Substation in New Haven and Milvon Substation in Milford. Final closeout activities continued on the Pequonnock Resiliency Project, which relocated and elevated critical infrastructure to reduce coastal flood risk.
In New York, subsidiaries New York State Electric & Gas and Rochester Gas and Electric completed or advanced substation modernisation projects. These included work at Fraser, Milo, Meyer, West Hill, Fourth Street, Cayuga Heights, Cobble Hill, Canandaigua and Aurora substations, alongside Substation 43 in Rochester.
In Maine, Central Maine Power energised upgrades at Stickney’s Corner and Bonney Eagle substations and completed the Rock Row 34 kV switchyard project. It also advanced battery replacements and automation improvements, with automated devices installed at eight substations.
Additional Connecticut work included telemetry, relay, communications and protection upgrades at substations and transmission facilities. Construction also began on permanent lightning protection improvements at East Shore Substation in New Haven.
Source: Yahoo Finance