India, Madhya Pradesh, Mandideep: CG Power and Industrial Solutions has approved an investment of $7.1 M (Rs.68 crore) to expand its T3 power transformer manufacturing facility, increasing capacity by 10,000 MVA to 75,000 MVA.

The plant is operating at maximum capacity. According to CG, a lean manufacturing initiative identified opportunities to increase output. The expansion is expected to take 12–15 months.

During July–September 2026, CG also inaugurated a transformer manufacturing facility at Sehore, Madhya Pradesh. The plant covers 20 ha (50 acres) and can produce 35 transformers per month.

At its S1 facility in Ambad, Nashik, CG plans to invest approximately Rs.300 crore to expand manufacturing of oil-impregnated paper bushings and instrument transformers rated up to 800 kV. Annual capacity would increase by 4,236 equivalent units to 11,436 equivalent units.

The S1 project includes additional manufacturing, assembly, testing and associated infrastructure. Production is tentatively expected to begin within 30–36 months.

CG said its switchgear facilities were experiencing peak capacity utilisation, with growing domestic and export demand for extra-high-voltage products.

The company’s Power Systems division, which includes transformers, reactors, circuit breakers, instrument transformers and bushings, recorded order inflow of $658 M (Rs.6,258 crore) during July–September 2026, more than double the year-earlier figure. Its order backlog stood at $2 B (Rs.18,964 crore) on 30 September, up 81 % year-on-year.