USA, Oregon, Eugene: Eugene Water and Electric Board (EWEB) has completed the upgrade of its Danebo Substation, which supplies electricity to around 6,000 customers in northwest Eugene.

The project includes a new transformer capable of delivering up to 65 % more power than the previous unit. EWEB said the additional capacity will provide greater flexibility during maintenance and unexpected equipment outages while supporting rising electricity demand.

The upgrade also focused on earthquake resilience. Transformer and equipment foundations were reinforced or deepened where necessary to withstand seismic forces, while flexible connections and cable interfaces were introduced to reduce the transfer of damaging forces between components during ground movement.

EWEB also replaced conventional mineral oil in the transformer with natural ester insulating fluid, which the utility says is less flammable and readily biodegradable.

Originally constructed during the 1960s, Danebo is one of 38 substations within EWEB’s electricity network. The utility is carrying out a wider modernisation programme to address ageing infrastructure over the next decade.

As part of its latest 10-year infrastructure investment plan, EWEB has deferred the rebuilding of six substations by three to five years to limit the impact on customer rates. The postponed work represents approximately $65 M in investment.

The next major substation project is the Jessen Substation, which is scheduled for a complete rebuild.