Kenya: Kenya has energised the 400/ 220 kV Mariakani substation, a major step in improving electricity supply across the Coastal region. The project is expected to deliver more reliable power to households, businesses, hotels and both small and large manufacturing industries.
Kenya Electricity Transmission Company (KETRACO) said the Mariakani substation is a vital gateway connecting the Coast to Nairobi’s national transmission grid. The 400 kV reinforcement will strengthen power stability, support industrial expansion, attract investment and improve everyday life for millions of Kenyans.
The substation forms part of the Nairobi–Mombasa Transmission Line and is designed to carry more than 1,000 MW of electricity between the two regions. This will ease pressure on the Coast’s power network and improve overall grid performance. According to KETRACO, the project is a key element in reinforcing Kenya’s national transmission system, which also supports the wider regional interconnected grid.
Strengthening the grid is seen as essential to fully benefit from the 500 kV Ethiopia–Kenya and 400 kV Kenya–Tanzania interconnectors. These links help move power more efficiently across borders and regions.
KETRACO added that the Mariakani substation will also support Kenya’s goal of achieving 100 % clean energy by 2030. It will allow more geothermal power from Olkaria, wind energy from the Lake Turkana Wind Power project, and hydropower from Ethiopia to reach the Coast.
Acting Managing Director Kipkemoi Kibias said the development will greatly reduce the region’s reliance on costly and polluting diesel generation, especially during peak evening demand. Cleaner and more stable energy is expected to lower costs and improve reliability.
The project, costing $23 M (KES 3 B), was funded by the Government of Kenya and the African Development Bank. China CAMC Engineering Company implemented the works, supervised by KETRACO engineers.
Source: ESI Africa