The Netherlands, Schiedam: Two offshore substations built by Smulders HSM and engineering partner Iv have departed Dutch fabrication yards for installation in the German Baltic Sea as part of 50Hertz’s OST-6-1 grid connection project.
The topsides and steel jacket foundations for OSS Zingst and OSS Darß sailed from Schiedam and Vlissingen, respectively. Each substation has a capacity of approximately 450 MW and will form part of the offshore electrical infrastructure connecting the 927 MW Gennaker Offshore Wind Farm to Germany’s transmission network.
The structures were delivered by the HSI Joint Venture, combining Smulders HSM and Iv. The consortium is responsible for engineering, procurement, construction, transport, installation and commissioning of both substations.
OSS Zingst was assembled and integrated in Schiedam, while OSS Darß was prepared in Vlissingen.
The substations will collect electricity generated by the wind farm and support its transfer towards the mainland grid. With the topsides and jackets now at sea, the project is moving into the offshore installation, systems integration and commissioning phase.
The remaining scope includes positioning the structures offshore and completing their integration into the OST-6-1 connection infrastructure.
Source: Breakbulk.News