substation_Shutterstock_2475409533
Image for illustrative purposes

USA, New Jersey, Ocean County: Jersey Central Power & Light (JCP&L) has announced it will invest $108 M in Ocean County’s electricity network through 2028, citing rapid population growth and a sharp increase in requests for new power connections. The county has grown by 30,000 residents since 2020, while developers have applied for more than 50 MW of new demand in the past year.

According to the utility, existing planning models no longer accurately reflect how quickly demand is rising. The company intends to reinforce the grid with a mix of line upgrades, stronger equipment and substation expansion.

A major component of the plan involves $29 M allocated to phase two of the New Jersey Reliability Improvement Project. Scheduled between 2026 and 2028, the work will target areas with frequent outages, including Lacey, Lakehurst, Manchester and Berkeley. Planned upgrades include thicker and more resilient wires and poles, along with additional protection systems and automatic transfer devices designed to reroute electricity during faults.

In the near term, JCP&L expects to complete $21 M in improvements across Ocean County this year. The work includes the installation of two new transformers and the upgrade of another at a local substation to increase available capacity. Line upgrades are also planned for Toms River, Lakewood and Jackson.

The remaining $58 M is tied to EnergizeNJ, a wider grid investment programme approved in April 2025 by the New Jersey Board of Public Utilities. The programme focuses on substation modernisation, system resilience and grid strengthening.

Source: Patch