UK, Pelham: National Grid has removed two existing transformers from Pelham Substation as part of its North London Reinforcement project.
Each transformer weighed approximately 180 t and had been in service for around 35 years. Their removal clears the site for two new quad boosters designed to increase the amount of electricity the substation can transmit and support system balancing.
The transformers were decommissioned in phases over approximately one month each. During the process, teams inspected internal components to assess their condition and performance over time. National Grid said the findings will help inform future transformer design and asset management.
After inspection, the main transformer sections were removed by heavy-lift crane and transported off site for disposal and recycling. Supporting equipment, including the noise enclosure and air-insulated switchgear, was also removed.
Work is now underway on piling and foundations for the replacement equipment. Each new quad booster will weigh around 300 t and will be transported to Pelham in four separate heavy-lift movements.
Delivery is scheduled between February and April 2027.
The wider project will also include rerouting part of an overhead line, undergrounding cables and removing 11 pylons around the substation. The existing line between Pelham and Waltham Cross will be upgraded with higher-voltage cables.
Source: National Grid