USA, Washington: Puget Sound Energy (PSE) has received approximately $40.2 M from the US Department of Energy for transmission upgrades under Project PULSE. PSE will match the grant, bringing the total investment to approximately $80.4 M.

Proposed work between 2027 and 2031 includes upgrading four existing 115 kV transmission line segments spanning approximately 23 miles in King and Kitsap counties. PSE estimates that $21 M will fund reconductoring and upgrade work in Kitsap County.

The project also includes deploying 178 dynamic line rating sensors across 520 km (323 mi) of transmission lines in Skagit, Snohomish, King, Pierce, Kittitas and Thurston counties, alongside grid-monitoring software.

According to PSE, the upgrades are intended to increase capacity and flexibility on existing transmission infrastructure and address constrained sections of the network. The utility said this approach could defer more expensive infrastructure investments as electricity demand grows across the Puget Sound region.

Project PULSE, short for Puget Upgrades for Line Capacity, System Flexibility, and Energy Resilience, is supported through DOE’s SPARK programme, which covers 31 projects nationwide.